|
Production balance in spinning mills
by Dr. H.R.Sheikh,
professor, Emeritus, Textile Institute of Pakistan.
Entrepreneurs must fulfill many important requirements in
order to set up viable yarn manufacturing plants. Some of these
requirements are selection of most suitable site and machinery
combination, economic size of the unit and operational
flexibility. However, once the plant has been installed and
commissioned, spinning managers endeavour to achieve the
required product quality at standard output rate. Therefore, it
is necessary to maintain production balance between preparatory,
spinning and winding stages and ensure the following parameters:
- No section of any winding machine should be out of
production due to shortage of yarn supply from the ring
spinning shed.
- Similarly, the ring spinning frame or any back process
machine should not be idle due to shortage of feed material.
- There should not be an excessive stock of yarn, roving,
sliver and blowroom laps, as accumulation of material at any
processing stage may lead to temporary stoppage of the back
process machine.
- Machines should not be operated at maximum speed in order
to consume the accumulated stock of back process materials.
1. Economic size of the spinning
unit
The installed capacity of spindles for an economic size unit
has progressively increased in Pakistan. During the eighties a
spinning mill with an installed capacity of about 14000/15000
spindles was considered to be an economic unit. However with the
commencement of World Free Trade Regime (W.T.O) the textile
industry of Pakistan is facing multiple challenges. The textile
and clothing products can find access in the international
export market only on the basis of the required quality and
competitive price. With an escalation in the prices of all
inputs, currently, a spinning unit with an installed capacity of
about 20160 spindles is considered to be an economic unit. This
would require installation of 40 Ring Spinning Frames with 504
spindles each.
2. Production program ring spinning
Assuming that the installed capacity of the spinning mill is
20,160 spindles comprising of 40 Ring Spinning Frames, the daily
production will depend upon the production program. A typical
production program for ring spinning machines is tabulated
below.
|
Nominal yarn count |
|
Particulars |
10 |
16 |
20 |
30 |
| Actual
count (Ne) |
10.20 |
16.20 |
20.20 |
30.20 |
| Spindle
speed (RPM) |
11,000 |
16,000 |
16,800 |
17,500 |
| Twist
factor |
4.2 |
4.2 |
4.2 |
4.25 |
| Turns
per inch |
13.41 |
16.91 |
18.88 |
23.36 |
| OPS
100% (ozs per spindle shift) |
20.43 |
14.84 |
11.19 |
6.3 |
| Efficiency
% |
88 |
92 |
92 |
93 |
| Actual
OPS |
17.98 |
13.65 |
10.30 |
5.86 |
| Production
per Ring Frame per day – (504 Spindles ) in Lbs. |
1699.11 |
1289.93 |
973.35 |
553.77 |
| Allocation
of ring frame |
2 |
6 |
20 |
12 |
| Daily
production count-wise (in Lbs.) |
3398.22 |
7739.58 |
19467 |
6645.24 |
|
Total Daily
Production = 37250.04 Lbs. |
Average Yarn Count =
10.2×3398.22+16.2×7739.58+20.2×19467+30.2×6645.24
37250.04
= 753962.67 =20.24 Ne
37250.04
2.1. Simplex frames
For the supply of roving to the ring shed operating in
accordance with the above production program two types of roving
hanks have been selected. Roving hank of 0.80 for yarn counts of
10.20 Ne and 16.20 Ne. and roving hank of 1.0 for yarn counts of
20.20 Ne and 30.20 Ne. The number of hanks of roving is
generally kept as small as possible. The objectives are to
facilitate balancing of production, implementation of colour
scheme and elimination of mixed yarn production. On the basis of
the foregoing assumptions, the number of Simplex frames required
to supply roving to be ring shed are calculated as follows:
|
Actual yarn count |
|
Particulars |
10.2 & 16.2 |
20.2 & 30.2 |
Remarks |
|
Daily yarn production (LBS)
|
11, 137.80 |
26,112.24 |
|
|
Production required from
simplex frames with 3% waste in ring spinning. |
11,471.93 |
26,895.61 |
|
|
Hank of roving |
0.8 |
1.0 |
|
|
Twist factor and turns per
inch |
0.85/0.76 |
1.0/1.0 |
|
|
Flyer speed (RPM) |
1,100 |
1,100 |
|
|
Delivery in inches per minute |
1,447,37 |
1,100 |
|
|
100% production per spindle
per day (LBS) |
86,15 |
52.38 |
|
|
Actual production /spindle/day |
73.23 |
44.52 |
Efficiency =
85% |
|
No. of simplex frames spindles
required |
156.66 |
604.12 |
|
|
No. of simplex frames required |
1.31 |
5.03 |
Simplex frame
with 120 spindles each. |
|
Total number of Simplex
frames = 6.34 or 7.0 |
2.2 Drawing frames ( 2 Passage)
Assuming waste of 0.50 % at the roving stage, production
required from the Drawing Frames works out as:
11471.93+26895.61) × 1.005 = 38367.54×1.005 = 38559.38 LBS
Linear Density of finished sliver = 70 grains per yard = 0.119
Delivery speed of Drawing Frames = 400 MPM.
Production of one set of Drawing Frame (double delivery) per day
at 85 % efficiency equals to:
400×1.0936×60×24×0.85×2
=10712.82 LBS
0.119840
Number of Drawing Frames (Finisher) required 38559.38
= 3.6 say 4sets.
10712.82
Assuming linear density of sliver at Breaker Drawing Frame is
equal to 70 grains per yard, delivery speed equal to 400 MPM and
waste at the Finisher Drawing Frames at 0.25 %, production
required from Breaker Drawing Frames works out at
38559.38×1.0025 = 38655.78 LBS.
Production of one Drawing Frame (Breaker) = 10712.82 LBS.
Number of Drawing Frames (Breaker required) = 38655.78
= 3.61 say 4 sets.
10712.82
2.3. Cards
Assuming waste at the Breaker Drawing Frames at 0.25 %,
production required from the cards works out at =
38655.78×1.0025 = 38752.419 LBS.
Linear density of card sliver = 70 grains per yard = 0.119.
Delivery speed = 145 MPM. Efficiency of card = 86 %.
Production of card per day = 145×1.0936×60×24×0.86 =
1964.54 LBS
0.119×840
Number of cards required = 38752.419 =
19.73 or say 20 cards
1964.54
Usually 2 extra cards will be installed to add flexibility to
the carding process and take care of stoppage of any card for
replacement of old wire.
2.4. Blowroom
Daily production required from Blow Room Line @ 7 % waste at
the carding stage 38752.419 × 1.07 = 41465.09 LBS. Production
required per hour = 1727.71 LBS = 783.68 KG.
If Chute Feed System is not provided, number of scutchers
required is calculated as follows:
Diameter of Lap Roller = 9 inch.
Speed of Lap Roller = 15 RPM.
Linear density of Lap = I LB/yard, Efficiency = 85 %
Hank of Lap = 0.00119
Production per scutcher per day= TT ×9×15×60×24×0.85
= 14431.68 LBS
36×0.00119×840
Number of scutchers required = 41465.09 = 2.87 or
say 3 scutchers.
14431.68
2.5 Cotton Required.
The quantity of cotton required per day can be calculated is
shown in the next column:
2.6. Auto – cone winding machines
Cotton required per day @ 7 % waste in Blow Room = 41465.09 ×
1.07 = 44367.65 LBS.
Number of cotton bales required (375 LBS each) is equal to:
44367.65 = 118.3 or say 119 bales.
375
The ring cops produced on the Ring Spinning Frames are not
marketable. In order to produce cones which are marketable,
winding of ring cops is carried out on Auto-Cone Winding
Machines.
The number of winding machines required is calculated as
follows:
|
Nominal/Actual Yarn Count |
|
Particulars |
10/10.2 |
16/16.2 |
20/20.2 |
30/30.2 |
| Daily
production (LBS) |
3398.22 |
7739.58 |
19467 |
6645.24 |
| Winding
speed (MPM) |
1000 |
1050 |
1100 |
1200 |
| Operating
efficiency |
85% |
85% |
85% |
85% |
| Production
per drum per day (LBS) |
156.23 |
103.28 |
86.78 |
63.32 |
| No.
of drums required |
21.75 |
74.94 |
224.33 |
104.95 |
Total number of drums required = 21.75+74.94+224.33+104.95 =
425.97
Number of winding machines required (60 drums each) is equal
to: 425.97 = 7.0995 or say 7 machines.
60
Summary
Process wise number of machines calculated above for
achieving production balance are summarized below:
- Ring Spinning Economic Unit = 20,160 spindles, 40
Ring Spinning Frames, 504 spindles each.
- Simplex Frames, 7 Roving Frames, 120 spindles each.
- Drawing Frames, (2 Passage), 4 Double Delivery Drawing
Frames.
- Carding Machines, 22 cards.
- Blow Room, cleaning Line of machines with Chute Feed
System or 3 Single Process Scutchers.
It may also be pointed out that leading textile machinery
manufacturers are marketing modern state of the art machines
with operating speeds higher than those used in the foregoing
calculations. Many entrepreneurs would like to install these
machines at their Spinning Mills, and above mentioned machinery
combinations are determined by the financial resources and the
investment capabilities of the respective entrepreneurs as well
as presently installed spinning mills in Pakistan.
Acknowledgement
Assistance received from Tanzeel Minhaj, Bilal Ahmed,
Muhammad Adnan and Danyal Siddiqui (Final year students of T.I.P.)
is gratefully acknowledged.
|